Date |
Status information |
| Thursday 3/21/13 |
The County has procured the services of a civil engineering consultant, Dokken Engineering, to complete the design for the repair to Nelson Road. They have recently completed necessary field work and are currently in the process of preparing the preliminary roadway alignment and associated drainage and structural improvements. The project is currently scheduled to be constructed in the summer of 2014.
|
| Tue 2/21/12 |
Focused Engineering Geologic Investigation of the Nelson Road Landslide
|
| Tue 12/12/11 |
Starting Monday, December 26, 2011, GreenWaste will remove the garbage and recycling bins at the current location and pickup will return to the original preslide method and locations.
|
| Tue 10/18/11 |
The paving operation for the bypass road has been rescheduled for Thursday, October 20, 2011 between the hours of 9:00 am and 4:00 pm
|
| Thu 10/13/11 |
The paving operation for the bypass road is scheduled for Tuesday, October 18, 2011. As a reminder, the paving operation will close down the bypass road to through traffic during the working hours from 9am to 4pm.
|
| Wed 10/05/11 |
The temporary bypass road winterization work is scheduled to begin Monday, October 10, 2011 and will continue through Tuesday, October 18, 2011 from 9:00 a.m. to 4:00 p.m. each day. Be prepared for delays of up to 30 minutes.
|
| Fri 7/29/11 |
California Delegation Letter to the President in Support of the State of California's appeal for federal disaster assistance related to the March 2011 severe storm system disaster.
|
| Mon 7/25/11 |
California Emergency Management Agency (Cal EMA)
Video regarding 2011 Spring Storms
|
| Wed 6/29/11 |
The geologist has completed the large diameter boring investigation and will start the small diameter boring investigation as planned on Tuesday, July 5, 2011. We ask that the areas of work designated by the white spray paint and access to those areas remain unobstructed.
|
| Fri 6/24/11 |
The geologist will be performing the large diameter borings from Tuesday, June 28, 2011 through Thursday, June 30, 2011 from 8:30am to 4:30 am daily. The small diameter borings will occur Tuesday, July 5, 2011 through Friday, July 8, 2011 from 8:30am to 4:30pm daily. We anticipate that these operations will have minimal impacts to road access. The areas of work have been marked with white spray paint.
|
| Fri 5/20/11 |
There is no new information.
|
| Wed 5/4/11 |
The community meeting tentatively scheduled for Tuesday, May 10, 2011, has been cancelled. The County has no new information to present at this time.
|
| Wed 5/4/11 |
The temporary bypass road requires some minor adjustments. This work will start on Wednesday, May 4, 2011, between the hours of 8:30 am and 5:00 pm and is expected to take 5 days. Please be prepared for delays of up to 10 minutes. The work includes widening the temporary bypass road at several locations, protecting the existing culvert, fixing potholes and installing a road bump on Eclectia driveway near the well. The paving work will require a temporary closure of the bypass road from 8:30 am to 5:00 pm on Monday, May 9, 2011.
|
| Wed 4/6/11 |
The trash bin and recycling bin have been relocated onto Nelson Rd near the cluster of mailboxes just north of the temporary detour road.
|
| Tue 4/5/11 |
The temporary detour road was completed on Saturday, 4/2/11 and was open to traffic. The load limit is 5 tons except for emergency vehicles and propane trucks.
|
| Fri 4/1/11 |
The construction crews have been working extremely hard in constructing the temporary road; however, their progress has been slowed because of some extremely wet areas near the creek. Therefore the completion of the temporary road has been rescheduled to the afternoon of Saturday, 4/2/11
|
|
Fri 04/01/11 (tentative) |
Proposed
completion date for temporary road construction. |
|
Thur 3/31/11 |
One trash bin and one recycle bin were delivered. The bins are located at 1165 Nelson Rd. At this time there is no service for the individual carts.
|
| Wed 3/30/11 |
The culvert for the
temporary road has been installed and work is progressing on the
temporary road on the west side of the creek. |
|
Tue 3/29/11 |
Rock
and fabric being placed for temporary road, with plans to install culverts to cross
the creek. |
|
Mon 3/28/11 |
Temporary
access Road construction - A path has been cut down to the creek. |
|
Mon 3/28/11 |
A
Geologist performed an on-site field investigation.
Findings: The Nelson Road slide is still quite wet and unstable.
Therefore road clearing can't start until conditions improve.
|
|
Sat 03/26/11 |
Construction
of temporary road halted due to extremely wet conditions |
|
Fri 03/25/11 |
Began
construction of a temporary access road around the slide |